In Kenya building a permanent house is controlled by the Physical and Land Use Planning Act 2019, Building Code 1968/2009, EMCA 1999 and County bylaws. You must get approvals before you break ground.
Here are the legal steps:
1. Confirm Land Ownership & Suitability
- Have original title deed, ID, KRA PIN
- Do an official land search at Ministry of Lands (not older than 6 months)
- Get beacon certificate from licensed surveyor. If land is leased, get consent from landlord / National Land Commission. Land must be free from disputes or riparian reserve (4m to 30m from river/lake)
2. Engage Registered Professionals Only
By law, design and supervision must be done by registered professionals:
- Physical Planner (if change of user needed)
- Registered Architect - to draw architectural plans
- Registered Structural / Civil Engineer - structural drawings
- Quantity Surveyor, EIA Expert
Using unregistered draftsmen leads to automatic rejection.
3. County Government Development Permission
This is the main approval. Apply through your County e-DPermit / e-Construction portal with:
- Site plan, Floor plans, Elevations, Sections, Roof plan
- Stamped drawings by Architect and Engineer
- Title deed + Search, PLUPA forms
- Rates clearance, approval fee - typically 0.5% to 1% of estimated construction cost
You get approved drawings (blueprints) and a Building Permit letter with conditions. Approval lapses if you don't submit plans within 1 year and start construction within 2 years.
If your land zoning is agricultural, you first need Change of User / Extension of User from County Planning Department.
4. NEMA - Environmental Compliance
All permanent houses need NEMA approval.
- Low-risk (single dwelling): Submit Project Report Summary via licensed EIA expert. Pay 0.1% of project cost (min KES 10,000).
- NEMA must respond within 45 days for low-risk projects.
Without NEMA license, you can be fined or house demolished.
If near a river, also get WRA (Water Resources Authority) approval.
5. Register Project with National Construction Authority (NCA)
After County & NEMA approval, register project with NCA:
- Submit: approved drawings, NEMA license, contractor details, consultants, Bill of Quantities summary, KRA PIN, contract agreement
- Contractor MUST be NCA-licensed
NCA issues a compliance certificate and project registration.
6. During Construction - Inspections
County and NCA inspectors will do stage inspections (foundation, walling, roofing). Keep approved plans on site. If near airport, you also need KCAA clearance.
7. Post-Construction
- Apply for Occupation Certificate from County after final inspection
- Get compliance from public health, water and sewer connection approvals.